The Haven Protocol
Operator console · Simulated data
Emergency crude transfer

Installation study

Follow the oil from the surviving transfer trains to the actual buyer. The installation is evaluated for 72 hours of service or safe isolation when both receiving routes are lost.

Conditional rolling flow400.03 m³/hThree-second standby test with its own inlet seats.
One failed original inlet4.276 LSegmented-seat test, including supplementary oil. Zero retained.
Source schedules replayed20 of 20Eight unavailable piston pairs per train.
Installed missions verified0 of 20Physical performance and common failures remain open.

When the buyer fails mid-flow

With both buyer weights falsely healthy, 1,442.857 reference L crossed the paired original inlets. With an independent liquid-level witness and 20 ms segmented closing seats, 8.539 L crossed the paired main inlets. At peak flow, one buyer already admits 2.839 L in the 39.75 ms before the witness reacts. When both physical proofs also mimicked healthy receipt, 1,437.143 L crossed in 10.1 seconds. Each failed receiver retained zero. See the inlet measurements and jam tests.

Incident case register

Open a case for its required response and installation checks. The replayed source schedule has separate criteria from the full installation.

01Source closing energy lost and conventional valves jammedIsolate nowUnverified

Required outcome Keep the process source and both original buyer inlets isolated. Monitor stored inventory and exterior containment.

Original source replay The source was already isolated at second 80. Recorded post-stop transfer was 0 m³.

Open original gates Unannounced loss at the original inlet, Safe total-loss isolation and containment, Oil crossing the site boundary, Installed support response.

Installation assessment At second 80 the segmented original inlet was already closed. Gross crossing was zero. The thermal result depends on the selected geometry and retained coolant. Exterior containment, paired construction and installed supports still need verification.

02Terminal closing energy lost and conventional valves jammedIsolate nowUnverified

Required outcome Keep the process source and both original buyer inlets isolated. Monitor stored inventory and exterior containment.

Original source replay The source was already isolated at second 80. Recorded post-stop transfer was 0 m³.

Open original gates Unannounced loss at the original inlet, Safe total-loss isolation and containment, Oil crossing the site boundary, Installed support response.

Installation assessment At second 80 the segmented original inlet was already closed. Gross crossing was zero. The thermal result depends on the selected geometry and retained coolant. Exterior containment, paired construction and installed supports still need verification.

03Source and terminal closing energy lost with jammed conventional valvesIsolate nowUnverified

Required outcome Keep the process source and both original buyer inlets isolated. Monitor stored inventory and exterior containment.

Original source replay The source was already isolated at second 80. Recorded post-stop transfer was 0 m³.

Open original gates Unannounced loss at the original inlet, Safe total-loss isolation and containment, Oil crossing the site boundary, Installed support response.

Installation assessment At second 80 the segmented original inlet was already closed. Gross crossing was zero. The thermal result depends on the selected geometry and retained coolant. Exterior containment, paired construction and installed supports still need verification.

04Trigger inlets blocked with jammed conventional valvesIsolate nowUnverified

Required outcome Keep the process source and both original buyer inlets isolated. Monitor stored inventory and exterior containment.

Original source replay The source was already isolated at second 80. Recorded post-stop transfer was 0 m³.

Open original gates Unannounced loss at the original inlet, Safe total-loss isolation and containment, Oil crossing the site boundary, Installed support response.

Installation assessment At second 80 the segmented original inlet was already closed. Gross crossing was zero. The thermal result depends on the selected geometry and retained coolant. Exterior containment, paired construction and installed supports still need verification.

05Pilots blocked with jammed conventional valvesIsolate nowUnverified

Required outcome Keep the process source and both original buyer inlets isolated. Monitor stored inventory and exterior containment.

Original source replay The source was already isolated at second 80. Recorded post-stop transfer was 0 m³.

Open original gates Unannounced loss at the original inlet, Safe total-loss isolation and containment, Oil crossing the site boundary, Installed support response.

Installation assessment At second 80 the segmented original inlet was already closed. Gross crossing was zero. The thermal result depends on the selected geometry and retained coolant. Exterior containment, paired construction and installed supports still need verification.

06Sleeves torn with jammed conventional valvesIsolate nowUnverified

Required outcome Keep the process source and both original buyer inlets isolated. Monitor stored inventory and exterior containment.

Original source replay The source was already isolated at second 80. Recorded post-stop transfer was 0 m³.

Open original gates Unannounced loss at the original inlet, Safe total-loss isolation and containment, Oil crossing the site boundary, Installed support response.

Installation assessment At second 80 the segmented original inlet was already closed. Gross crossing was zero. The thermal result depends on the selected geometry and retained coolant. Exterior containment, paired construction and installed supports still need verification.

07Sleeve closing force tripled with jammed conventional valvesIsolate nowUnverified

Required outcome Keep the process source and both original buyer inlets isolated. Monitor stored inventory and exterior containment.

Original source replay The source was already isolated at second 80. Recorded post-stop transfer was 0 m³.

Open original gates Unannounced loss at the original inlet, Safe total-loss isolation and containment, Oil crossing the site boundary, Installed support response.

Installation assessment At second 80 the segmented original inlet was already closed. Gross crossing was zero. The thermal result depends on the selected geometry and retained coolant. Exterior containment, paired construction and installed supports still need verification.

085 mm² seat gaps with jammed conventional valvesIsolate nowUnverified

Required outcome Keep the process source and both original buyer inlets isolated. Monitor stored inventory and exterior containment.

Original source replay The source was already isolated at second 80. Recorded post-stop transfer was 0 m³.

Open original gates Unannounced loss at the original inlet, Safe total-loss isolation and containment, Oil crossing the site boundary, Installed support response.

Installation assessment At second 80 the segmented original inlet was already closed. Gross crossing was zero. The thermal result depends on the selected geometry and retained coolant. Exterior containment, paired construction and installed supports still need verification.

09Three route boundaries lostDeliver 72 hUnverified

Required outcome Continue through a verified receiving route while flow, quality, pressure, stored energy and containment remain within their limits.

Original source replay Native source floor 403.492 m³/h. Clock-aligned qualified oil floor 400.151 m³/h.

Open original gates Oil crossing the site boundary, Installed support response, Wet pathways separated from buyer inventory.

Installation assessment At second 80, false weights and a functioning independent liquid-level witness gave 4.276 L gross into one failed original inlet with the segmented seats. The receiver retained zero. Exterior escape is unresolved. The thermal result depends on the selected geometry and retained coolant. Exterior containment, paired construction and installed supports still need verification.

10Independent heat envelope penetratedDeliver 72 hUnverified

Required outcome Continue through a verified receiving route while flow, quality, pressure, stored energy and containment remain within their limits.

Original source replay Native source floor 403.492 m³/h. Clock-aligned qualified oil floor 400.151 m³/h.

Open original gates Oil crossing the site boundary, Installed support response, Wet pathways separated from buyer inventory.

Installation assessment At second 80, false weights and a functioning independent liquid-level witness gave 4.276 L gross into one failed original inlet with the segmented seats. The receiver retained zero. Exterior escape is unresolved. The thermal result depends on the selected geometry and retained coolant. Exterior containment, paired construction and installed supports still need verification.

11Closed catch boundary lostIsolate nowUnverified

Required outcome Keep the process source and both original buyer inlets isolated. Monitor stored inventory and exterior containment.

Original source replay The source was already isolated at second 80. Recorded post-stop transfer was 0 m³.

Open original gates Unannounced loss at the original inlet, Safe total-loss isolation and containment, Oil crossing the site boundary, Installed support response.

Installation assessment At second 80 the segmented original inlet was already closed. Gross crossing was zero. The thermal result depends on the selected geometry and retained coolant. Exterior containment, paired construction and installed supports still need verification.

12Loaded collapse and outer-vault loss at 60 hStop at 60 hUnverified

Required outcome Maintain verified receiving flow to hour 60, then isolate and account for oil in the buyer, catch and exterior.

Original source replay Native source floor 403.492 m³/h. Clock-aligned qualified oil floor 400.151 m³/h. The hour-60 source stop recorded 0 m³ of later transfer.

Open original gates Unannounced loss at the original inlet, Loaded liquid and gas capture through hour 72, Safe total-loss isolation and containment, Oil crossing the site boundary, Installed support response, Wet pathways separated from buyer inventory.

Installation assessment At second 80, false weights and a functioning independent liquid-level witness gave 4.276 L gross into one failed original inlet with the segmented seats. The receiver retained zero. Exterior escape is unresolved. The depleted water cassette and the raised-floor hot start both miss the 1.33 kPa pressure target in this case. Exterior containment, paired construction and installed supports still need verification.

13100 mm source-gas wall breachDeliver 72 hUnverified

Required outcome Continue through a verified receiving route while flow, quality, pressure, stored energy and containment remain within their limits.

Original source replay Native source floor 403.492 m³/h. Clock-aligned qualified oil floor 400.151 m³/h.

Open original gates Oil crossing the site boundary, Installed support response, Wet pathways separated from buyer inventory.

Installation assessment At second 80, false weights and a functioning independent liquid-level witness gave 4.276 L gross into one failed original inlet with the segmented seats. The receiver retained zero. Exterior escape is unresolved. The thermal result depends on the selected geometry and retained coolant. Exterior containment, paired construction and installed supports still need verification.

14Gas heat transfer degradedDeliver 72 hUnverified

Required outcome Continue through a verified receiving route while flow, quality, pressure, stored energy and containment remain within their limits.

Original source replay Native source floor 403.492 m³/h. Clock-aligned qualified oil floor 400.151 m³/h.

Open original gates Oil crossing the site boundary, Installed support response, Wet pathways separated from buyer inventory.

Installation assessment At second 80, false weights and a functioning independent liquid-level witness gave 4.276 L gross into one failed original inlet with the segmented seats. The receiver retained zero. Exterior escape is unresolved. The thermal result depends on the selected geometry and retained coolant. Exterior containment, paired construction and installed supports still need verification.

15Catch heat transfer reduced at 60 hStop at 60 hUnverified

Required outcome Maintain verified receiving flow to hour 60, then isolate and account for oil in the buyer, catch and exterior.

Original source replay Native source floor 403.492 m³/h. Clock-aligned qualified oil floor 400.151 m³/h. The hour-60 source stop recorded 0 m³ of later transfer.

Open original gates Unannounced loss at the original inlet, Safe total-loss isolation and containment, Oil crossing the site boundary, Installed support response, Wet pathways separated from buyer inventory.

Installation assessment At second 80, false weights and a functioning independent liquid-level witness gave 4.276 L gross into one failed original inlet with the segmented seats. The receiver retained zero. Exterior escape is unresolved. The thermal result depends on the selected geometry and retained coolant. Exterior containment, paired construction and installed supports still need verification.

16Local pocket outer boundary lostDeliver 72 hUnverified

Required outcome Continue through a verified receiving route while flow, quality, pressure, stored energy and containment remain within their limits.

Original source replay Native source floor 403.492 m³/h. Clock-aligned qualified oil floor 400.151 m³/h.

Open original gates Oil crossing the site boundary, Installed support response, Wet pathways separated from buyer inventory.

Installation assessment At second 80, false weights and a functioning independent liquid-level witness gave 4.276 L gross into one failed original inlet with the segmented seats. The receiver retained zero. Exterior escape is unresolved. The thermal result depends on the selected geometry and retained coolant. Exterior containment, paired construction and installed supports still need verification.

17Catch heat transfer lost at 60 hStop at 60 hUnverified

Required outcome Maintain verified receiving flow to hour 60, then isolate and account for oil in the buyer, catch and exterior.

Original source replay Native source floor 403.492 m³/h. Clock-aligned qualified oil floor 400.151 m³/h. The hour-60 source stop recorded 0 m³ of later transfer.

Open original gates Unannounced loss at the original inlet, Safe total-loss isolation and containment, Oil crossing the site boundary, Installed support response, Wet pathways separated from buyer inventory.

Installation assessment At second 80, false weights and a functioning independent liquid-level witness gave 4.276 L gross into one failed original inlet with the segmented seats. The receiver retained zero. Exterior escape is unresolved. The thermal result depends on the selected geometry and retained coolant. Exterior containment, paired construction and installed supports still need verification.

18Enclosure gas starts at 86°CStop at 60 hUnverified

Required outcome Maintain verified receiving flow to hour 60, then isolate and account for oil in the buyer, catch and exterior.

Original source replay Native source floor 403.492 m³/h. Clock-aligned qualified oil floor 400.151 m³/h. The hour-60 source stop recorded 0 m³ of later transfer.

Open original gates Unannounced loss at the original inlet, Loaded liquid and gas capture through hour 72, Safe total-loss isolation and containment, Oil crossing the site boundary, Installed support response, Wet pathways separated from buyer inventory.

Installation assessment At second 80, false weights and a functioning independent liquid-level witness gave 4.276 L gross into one failed original inlet with the segmented seats. The receiver retained zero. Exterior escape is unresolved. The depleted water cassette and the raised-floor hot start both miss the 1.33 kPa pressure target in this case. Exterior containment, paired construction and installed supports still need verification.

19Catcher shield fully openStop at 60 hUnverified

Required outcome Maintain verified receiving flow to hour 60, then isolate and account for oil in the buyer, catch and exterior.

Original source replay Native source floor 403.492 m³/h. Clock-aligned qualified oil floor 400.151 m³/h. The hour-60 source stop recorded 0 m³ of later transfer.

Open original gates Unannounced loss at the original inlet, Loaded liquid and gas capture through hour 72, Safe total-loss isolation and containment, Oil crossing the site boundary, Installed support response, Wet pathways separated from buyer inventory.

Installation assessment At second 80, false weights and a functioning independent liquid-level witness gave 4.276 L gross into one failed original inlet with the segmented seats. The receiver retained zero. Exterior escape is unresolved. The depleted water cassette and the raised-floor hot start both miss the 1.33 kPa pressure target in this case. Exterior containment, paired construction and installed supports still need verification.

20All current quality evidence falsifiedDeliver 72 hUnverified

Required outcome Continue through a verified receiving route while flow, quality, pressure, stored energy and containment remain within their limits.

Original source replay Native source floor 403.492 m³/h. Clock-aligned qualified oil floor 400.151 m³/h.

Open original gates Oil crossing the site boundary, Installed support response, Wet pathways separated from buyer inventory.

Installation assessment At second 80, false weights and a functioning independent liquid-level witness gave 4.276 L gross into one failed original inlet with the segmented seats. The receiver retained zero. Exterior escape is unresolved. The thermal result depends on the selected geometry and retained coolant. Exterior containment, paired construction and installed supports still need verification.

Watch the system operate

How an unannounced loss unfolds

Two trains each operate with 152 working piston pairs and eight unavailable. In this fault, oil is already crossing the original buyer inlet at 75 hot L/s per train. A pair of false weight signals can persist while the actual destination stops retaining oil.

Physical eventAutomatic response and outcome
Fault at second 80A mechanical follower at the receiver detects the missing change in oil level after 39.75 ms. An independent dry coupling link detects physical loss of alignment. An internal diversion can leave that link aligned.
Isolate the original inletTwo spring-return seats close on opposite faces of the same inlet. A captive coupling waits for both seats and a purge stroke. The 0.5505 hot L joint charge per inlet has a sealed catch, seller return and a separate finite quarantine cylinder.
Open a proven spareAn independently primed chamber supplies the original positive-flow demand while the fresh source switches. Each installation has a 250 reference L working prime and a separate recovery stroke. A 3 s peak transfer calls for 214.286 L.
Continue genuine receiptA supplementary supply at each buyer starts with 14.4 reference m³ of net on-spec oil. Only the healthy buyer’s continuous 0.20 m³/h stream earns receipt. The spare has a 30 ms opening ramp in the modeled transfer.
Check the future destinationOil enters a local low-pressure chamber at the working buyer. A separate lift pump moves it to reserved tank space. The buyer must retain the oil; moving its pre-existing heel earns no new sale.
Original inlet controlsGross forward crossing
False weights alone, both buyers fail1,442.857 reference L, paired
Both seats closed before planned release0 L after separation
False weights, 39.75 ms local observation, 20 ms segmented seats8.539 L paired main. One failed inlet admitted 4.269 L main plus 0.007 L supplementary oil.
Late local observation at 80 ms, or both seats jam with drive unloading7.154 L or 9.691 L, respectively, into one failed inlet including supplementary oil.
Upstream seat jams aloneThe predicted negative absolute pressure invalidates the single-phase calculation. Crossing and closure are unresolved.
Both physical proofs mimic the healthy state1,437.143 reference L, paired over 10.1 s

Why the transfer cannot always be zero

At the native peak, one failed inlet admits 2.839 L before a trustworthy indication arrives at 39.75 ms. The selected seat calculation gives a minimum of 99.319 kPa absolute, 8.495 kPa maximum differential and 2.791 hot L of relief per arm. The healthy open seat retains only 65.7 Pa of headroom at a loss coefficient of 2.7. A coefficient of 5 fails.

What sustains a 72-hour transfer

Each standby yard has a 24 m radius tank with 15,000 reference m³ of available receiving space, a separate local chamber, 90 m of 400 mm header and independently powered lift equipment. A failed tank adds no receiving capacity.

Operating checkSelected resultFailure control
Rolling 60 s delivery400.03 m³/h at 3 s393.665 m³/h lower bound at 5 s. A half-rate supplementary feed gives 399.930 m³/h.
Lift and storage2.183 m³ peak chamber oil; 359.6 hot m³ tank space leftA delayed lift or a blocked header can fill the local chamber and interrupt receipt.
Stored electricity690.8 kWh available; 636.5 kWh requiredOne available bay has a 281.7 kWh deficit. Battery heat, contact and actual state of charge matter.
Fast header closure692.8 kPa absolute; 1,000 kPa assumed ratingThe 350 kPa option fails. An always-open absorber produced nonphysical negative absolute pressure on the finer mesh.
Supplementary feed24 mm bore; 22 mm effective diameter with depositsAt 0.5 Pa·s and 22 mm, 2.75 kPa remains after regulation. At 1.0 Pa·s the same path misses by 17.65 kPa.

Energy and pressure hardware

The selected electrical case uses two connected bays with two 257 kWh battery modules apiece. It assumes 80% initial battery health and a usable state-of-charge range of 12–96%. The pressure-rated header, end seats and anchors carry the initial closure wave. An isolated return recovers compressed oil after flow stops.

Product quality at custody

All 27,152 upstream lot tests passed the composition model. A buyer tank starting at 0.5% water gave 0.5165% in the first 44 m³ mixed lot. Starting at 5% gave 3.9569%, above the 1% limit. Also verify chloride at or below 5 mg/kg and sediment at or below 0.05% by mass. Quarantine the lot when the independent sample or reference is unreliable.

Oil held by the segmented seats

After 1,016 exchanges, a 20 µm oil film with 99% recovery leaves 0.442 reference L in reserve per arm. The coupled material balance gives 400.029 m³/h. A 50 µm film exhausts the reserve by 0.075 L per arm even though the one-minute rate clears 400.

Segmented seats and a five-second takeover

A 500 reference L prime and four isolated 0.20 m³/h lines per yard feed a separate 75 hot m³ standby buyer tank. With surface and film losses charged, 6,000 failure phases per trial gave a nominal 400.829 m³/h. At 100 ms notice, 80 ms opening, a 5 s switch and one added line lost, 8.583 L crossed the failed inlet and the healthy receiver sustained 400.264 m³/h. At 160 ms notice and 110 ms opening, crossing rose to 12.872 L and flow fell to 399.942 m³/h. Half the start gas also fails. Tank acceptance and containment need joint testing.

Where the oil and displaced gas go

A covered pair of spill bays surrounds each original receiving yard and its standby. The 5.25 m retaining wall has no low-level exterior drain. Beneath the floor, two steel skins enclose monitored dry compartments. Separate gas holders accept displaced air and vapor.

72-hour receiver controlPaired exterior result or limit
Original and standby stock in assigned bays; drains and passages closed0.999870 L. No liquid overtopped. The higher bay level reached 4.63 m.
One 10 µm through-defect per yard in solid 140 mm joint belts0.999940 L. The limit is 1 L total for both yards.
Same defects in ordinary 36 mm plate or a 12 mm common seam1.000141 L and 1.000683 L, respectively.
Both cargoes reach one blocked bay13,423 m³ of liquid overtops per yard. Oil fraction requires separate accounting.
All vapor connections blocked91.0 kPa gauge against a 6 kPa assumed limit. Exterior release is unresolved once that limit is exceeded.
Thermal water escapes both barriers1.464952 L. The added water can carry 0.465 L of oil-equivalent impurity at the specified concentration.

What the one-litre result requires

The site trace begins near 0.999798 L before new surface and leakage charges. The calculation assumes bounded surface cleanliness, wetting, flaw count and length in both yards. A common tear, spray over the wall, loss of vapor containment or leakage outside the two yards can exceed the allowance.

Construction scale

The modeled tertiary enclosure is 185 × 100 m per yard, with four proposed 45 m diameter variable-volume gas holders per train. The roof calculation alone uses 44,400 t of concrete across both yards. No installed assembly or construction price establishes commercial viability.

Thermal control and construction

The paired excavation limit applies to both trains and their supporting yards. Pressure depends on absolute gas charge, water temperature and the amount of coolant actually retained.

Site or utility checkOutcome
Hot-water margin3.476 kPa under nominal conditions. At reduced barometric pressure and low fill, 1.403 kPa remains against a 1.33 kPa target.
Backing cassette loses water0.232 kPa; cases 12, 18 and 19 miss the pressure target.
Thermal collectorA separate 413.20 m³ water catcher per train leaves 14.60 m³ under its modeled expansion and standpipe load. The extra water adds 310.05 m³ per train.
Excavation limit of 72.2 million m³With the thermal cassette and tertiary guard, 72,189,068 m³ nominal. The adverse top-down case reaches 72,201,534 m³ at 15 mm mean surface preparation.
Foundation and surface responseLower friction, failed anchorage or unexpected surface removal can consume the margin. Installed soil, welds, pipe restraints, media and room for construction have not been demonstrated.

Qualification work

Test independent receiver closure and single- and double-jam behavior at operating temperature. Meter every outlet during an isolated 72 h run with deliberately false local readings. Test finite tank free volume, loaded shutoff, vapor paths, thermal capacity, pressure-holding equipment, liner assemblies and surveyed foundations together.

What operators can verify here

The console displays modeled case duties, required actions, confidence limits and recorded results. Operational use would require independent, time-synchronized field records of retained inventory, inlet crossing, pressure, battery health, product grade, gas path and exterior collection. No live plant is connected.

Roof and thermal alternatives

A second layout puts the gas expansion volume directly above each loaded bay. A separately powered cooling loop provides another way to protect hot-water pressure. Each modification has its own failure tests.

AlternativeConditional result and adverse control
Add a 1 L spring diaphragm between the inlet seatsWith the upstream seat jammed, this option gave 88.693 kPa absolute, 33.086 kPa differential and 4.397 L crossing. Tenfold inertia gave 12.134 kPa and failed. With healthy seats, crossing was 4.293 L.
Move two gas bells above each yardWith all external gas connections lost, two independent moving roof bells held peak pressure to 2.699 kPa gauge. A 20 s fill reached 4.293 kPa against 6 kPa.
Bell motion is restrictedA jammed bell gave 661 kPa in its isolated bay, far outside the design envelope. An 8 m travel limit gave 72.14 kPa; abrupt gas heating gave 9.03 kPa. Moving seals and roof-ring foundations require verification.
Active cooling with the original 50 mm water layerAt a true 88°C start, a functioning pump with 15 min takeover gave 1.824 kPa water margin. At 30 min with weaker thermal contact it gave 1.821 kPa. Complete loss of the loop gave 0.296 kPa; cases 12, 18 and 19 missed 1.33 kPa.
Independent cooling assetsEach train needs 1,800 t of ice, a 2,000 m³ meltwater bund and dedicated circulation power. Only 0.565 m³ remains in the 56.05 m³ loop catcher after expansion. Total escape of the loop and meltwater could carry 2.779 L of oil, paired.
Construction scope with cooling at original floor gradeAll-face work gives 72,200,521 m³, 521 m³ over the cap. Floor-only credit and floor-only surface truing gives 72,199,413 m³, 587 m³ below it. Original six-face liner credit with floor-only truing gives 72,195,537 m³. A survey must establish the actual scope.
Raised real floorsRaising the usable floor patches gave 72,199,957 m³, leaving 43 m³. At a true 88°C start its minimum water margin was 0.621 kPa. Cases 12, 18 and 19 fail.
Alternative vault at original process-floor gradeThe profiled buyer vault gives 72,199,724 m³, 276 m³ below the cap. Its 6,103 m² of new developed skin creates at least 24,413 m² of additional guard surfaces. The 1 L exterior and water limits require verification on this geometry.

Separating fluids at the buyer

Under the water-cassette layout, wetted groups gave 0.698767 L/h of modeled water ingress against the 0.699 L/h limit. A common wet connection across all guard surfaces gave 0.700951 L/h. The incoming product, the original stored heel, retained spill and exterior contamination require separate records.